Dáil Éireann - Volume 539 - 26 June, 2001 Written Answers. - Coastal Protection Programme.
Mr. Bell Mr. Bell
191
[191] 97. Mr. Bell asked the Minister for the Marine and Natural Resources when the coastal protection programme for Annagassan, County Louth, will commence; the way in which the £200,000 allocation will be applied; the work which will be completed as part of the £6.86 million as indicated in March 2001; and if he will make a statement on the matter. [18895/01]
Mr. Fahey Mr. Fahey
192
Minister for the Marine and Natural Resources [192](Mr. Fahey): In March 2001, under the Coast Protection Programme for 2001, I approved £200,000 for phase 2 of the coast protection scheme at Annagassan, Co Louth. Louth County Council undertook this scheme directly. The county council has recently advised my Department that this scheme is now complete and the total expenditure on the scheme in 2001 is estimated to be in the region of £145,000. The bulk of this money was spent on 580 metres of 1.5 tonne rock armour revetment, 7,360 square metres of slope re-grading, 320 metres of cut-off drain, and 1,820 metres of herring bone drainage on slopes. Department of the Marine and Natural Resources Coast Protection Programme 2001.
County |
Location |
Project |
Cost 2001 (IR£) |
Louth |
Annagassan |
Phase 2 protection works |
£200,000 |
Dún Laoghaire/Rathdown |
Vico Road, Killiney |
Cliff protection works |
£700,000 |
Wicklow |
Bray |
Coast protection Phase 2 |
£300,000 |
|
Bray |
Pier remedial works |
£1,152,000 |
Wexford |
Courtown |
Detailed Design of offshore breakwater protection scheme |
£200,000 |
|
Courtown |
Revetment works |
£50,000 |
|
Cullenstown |
Revetment works and training walls |
£250,000 |
|
Rosslare Strand |
Study at North end of Spit |
£80,000 |
Dublin |
Bull Island |
Study |
£50,000 |
Cork |
Garretstown |
Road protection works |
£200,000 |
Kerry |
R561 Dingle to Castlemaine Road |
Revetment works |
£700,000 |
Clare |
Quilty |
Protection scheme |
£50,000 |
|
Clahanes, Liscannor |
Concrete Wall |
£150,000 |
Galway |
Sailin to Silver Strand |
Protection works |
£150,000 |
|
Auginish Island |
Causeway protection work |
£40,000 |
|
Inishbofin |
Protection works to South facing shore |
£100,000 |
|
Inishbofin |
Erosion Study of South facing shore |
£40,000 |
|
Renvyle |
Road protection works at Ard na Greevagh |
£50,000 |
|
Rusheenduff, Renvyle |
Coast protection |
£110,000 |
Mayo |
Westport / Bertra |
Dune protection |
£30,000 |
|
Belmullet Town |
Repair seawalls |
£100,000 |
|
Carrowmore Beach |
Dune protection |
£20,000 |
|
Roonagh, Louisburg |
Road protection works |
£30,000 |
|
Elly Bay |
Seawall repairs and dune protection |
£140,000 |
|
Mulranny Causeway |
Repairs to side/surface of causeway, repair stones |
£90,000 |
|
Bundoola, Belmullet |
Repairs to seawall |
£78,847 |
Sligo |
Mullaghmore |
Road protection works |
£283,000 |
|
Strandhill |
Slipway |
£140,000 |
|
Strandhill |
Shoreline protection |
£510,000 |
|
Pollacheeny |
Study and detailed design |
£32,000 |
Donegal |
Drung, Quigley's Point |
Rock Armour work |
£200,000 |
|
Keadue, Kincasslagh |
Seawall |
£250,000 |
|
Mountcharles |
Road Protection Works |
£300,000 |
|
Mahery, Dungloe |
Road Protection Works |
£100,000 |
|
Kerrykeel |
Road Protection Works |
£125,000 |
Waterford |
Tramore |
Promenade wall strengthening |
£1,112,937 |
|
Ballyvoile |
Study of road protection works |
£35,000 |
General |
Coastal Study |
Consultancy study of coast protection policy and priorities |
£200,000 |
|
East Coast |
Aerial survey/Carnsore to Killiney |
£30,000 |
|
Coastal Surveys |
General coastal and project related |
£50,000 |
|
Wave Buoys |
Maintenance and deployment |
£20,000 |
|
GIS System |
Customisation, maintenance and training |
£20,000 |