Dáil Éireann - Volume 179 - 18 February, 1960 Ceisteanna—Questions. Oral Answers. - Reconstruction of Kerry Embankments. Mr. Palmer Mr. Palmer 7. Mr. Palmer asked the Minister for Finance if he will state the cause of the delay in repairing the breaches on the Maine embankments at Callinafercy East, Milltown, County Kerry; and if he will ensure that the improvements will be carried out expeditiously so as to prevent further floodings of land and danger to livestock. Mr. J. Brennan Mr. J. Brennan Mr. J. Brennan: Reconstruction of these embankments will be carried out this year under the Maine Catchment Drainage Scheme. Mr. Palmer Mr. Palmer Mr. Palmer: Is the Parliamentary Secretary aware that at the present time, and for some months past, the lands in these areas have been seriously flooded so that the people cannot graze their cattle on the land or do any tillage? Is he not aware that last November the Land Commission, in conjunction with the Board of Works and the Parliamentary Secretary's section of the Department of Finance, agreed to close the breach temporarily to allow farmers to carry out their work in the ordinay way, pending the final completion of the work? Mr. J. Brennan Mr. J. Brennan Mr. J. Brennan: The Deputy should be satisfied with the answer I have given him. Mr. Palmer Mr. Palmer Mr. Palmer: No; I am not satisfied. Dáil Éireann 179 Ceisteanna—Questions. Oral Answers. Reconstruction of Kerry Embankments. Questions 19600218
| ||||||||||||||||||||||